July 5 Update

New Building Progress: July 5, 2017
by Doug T.
Renovation work on our new building began on June 16. A variety of materials, including doors and wood trim were salvaged. Most of the carpet and a lot of other unnecessary materials were disposed of. Our contractor has just begun removing the heating/cooling units located in most rooms.
The sub-contractor in charge of asbestos abatement and most of the demolition work has begun their work in rooms located on the second floor. They have taken down ceiling light fixtures and completed asbestos abatement in about a dozen rooms by now. It is an arduous process, designed to ensure their safety and ours. Soon they will be taking down some of the walls to create a part of our future sanctuary.